This guide explains everything you need to know before installing a solar PV system in Pakistan. Whether you are planning a small home solar system, a medium setup, or a large commercial solar PV system, this roadmap will help you understand the process from start to finish.
It is especially useful for people who want to install a grid-connected solar system and benefit from net metering in Pakistan.
What Is This Solar Net Metering Guide About?
This guide walks you through:
-
Planning a solar PV system
-
Understanding net metering rules
-
Applying for net metering with DISCO
-
Getting approval from NEPRA
-
Installing and connecting your solar system to the grid
It covers both residential solar installations and commercial solar PV systems.
Background: Why Solar Energy Is Important in Pakistan
Pakistan’s Energy Crisis Explained
Pakistan has been facing a serious energy crisis for many years. Electricity demand is much higher than supply, leading to:
-
Load shedding
-
Power blackouts
-
An energy shortfall of around 4000 MW
To reduce this gap, the Government of Pakistan is promoting renewable energy, especially solar power, through net metering.
What Is Net Metering in Pakistan?
Simple Explanation of Net Metering
Net metering allows solar users to:
-
Generate electricity for their own use
-
Send extra electricity to the national grid
-
Get credits or reduced electricity bills
If your solar system produces more power than you use, the extra units are exported to the grid. These units are adjusted against the electricity you consume later.
Who Benefits from Net Metering?
-
Homeowners with rooftop solar
-
Commercial buildings
-
Factories and offices
-
Any consumer with a three-phase electricity connection
NEPRA Net Metering Regulations in Pakistan
Official Net Metering Law
NEPRA introduced the Distributed Generation and Net Metering Regulations on September 1, 2015.
Under these rules:
-
Solar systems from 1 kW to 1 MW are allowed
-
Both residential and commercial users can apply
-
DISCOs must sign net metering agreements with eligible users
This policy is part of Pakistan’s Renewable Energy Policy 2006.
How to Apply for Net Metering in Pakistan – Step-by-Step
Step 1: Submit Net Metering Application
Apply to your relevant DISCO office with required documents.
The official application form is available on AEDB’s website.
Timeline: Application submitted anytime
Step 2: Application Acknowledgement
DISCO checks if your application is complete.
-
If documents are missing, you will be informed
-
You must resubmit missing information
Timeline:
-
Acknowledgement: within 5 working days
-
Missing documents: within 7 working days
Step 3: Initial Review by DISCO
DISCO reviews:
-
Technical eligibility
-
System capacity
-
Grid compatibility
Timeline: 20 working days
Step 4: Technical Feasibility Check
If the solar system is technically not feasible, the application is returned with reasons explained.
Step 5: Net Metering Agreement
If approved, the applicant and DISCO sign a net metering agreement.
Timeline: 3 working days after review
Step 6: Generation License from NEPRA
DISCO forwards the agreement to NEPRA to issue a generation license.
Timeline: 10 working days
Step 7: Connection Charge Estimate (CCE)
If grid upgrades or meter changes are needed:
-
DISCO issues a Connection Charge Estimate
-
Applicant pays the amount to the designated bank
If no upgrades are required, no CCE is issued.
Timeline:
-
Issuance: 7 working days
-
Payment: within 20 days
Step 8: Installation & Commissioning
After payment and license confirmation:
-
DISCO installs the bi-directional meter
-
System is connected to the grid
Now you can officially use net metering.
Net Metering Fees in Pakistan
Who Pays What?
-
Solar user pays all interconnection costs
-
Solar user pays for meter installation
-
Solar user covers any grid upgrade costs
NEPRA Generation License Fee Structure
| Solar System Size | Fee |
|---|---|
| 0–20 kW | Free |
| 20–50 kW | Rs. 500 |
| 50–100 kW | Rs. 1,000 |
| 100–1000 kW | Rs. 5,000 |
Final Thoughts for Solar Users in Pakistan
Net metering is one of the best benefits for solar users in Pakistan. It helps:
-
Reduce electricity bills
-
Earn credits on extra power
-
Support clean and renewable energy
If you plan properly and follow all steps, installing a grid-connected solar system can be a smart long-term investment.
Read More: Punjab Announces 100,000 Electric Bikes for Students


2 Comments
Needed an alternative and tried pk7app. Found what I needed ASAP and the app works great. Try them at pk7app.
M88est… feels like a good vibe here. Let’s see if Lady Luck is on my side tonight. Gonna roll the dice! Place your bets on m88est!